$\left(A + B\right)$s 20 days work =$ \left(\dfrac{1}{30} \times 20\right) $=$ \dfrac{2}{3} $.
Remaining work =$ \left(1 -\dfrac{2}{3} \right) $=$ \dfrac{1}{3} $.
Now,$ \dfrac{1}{3} $work is done by A in 20 days.
Therefore, the whole work will be done by A in $\left(20 \times 3\right)$ = 60 days.
P can complete the work in $\left(12 \times 8\right)$ hrs. = 96 hrs.
Q can complete the work in $\left(8 \times 10\right)$ hrs. = 80 hrs.
$\therefore$ Ps1 hours work =$ \dfrac{1}{96} $and Qs 1 hours work =$ \dfrac{1}{80} $.
$\left(P + Q\right)$s 1 hours work =$ \left(\dfrac{1}{96} +\dfrac{1}{80} \right) $=$ \dfrac{11}{480} $.
So, both P and Q will finish the work in$ \left(\dfrac{480}{11} \right) $hrs.
$\therefore$ Number of days of 8 hours each =$ \left(\dfrac{480}{11} \times\dfrac{1}{8} \right) $=$ \dfrac{60}{11} $days = 5$ \dfrac{5}{11} $days.
$\left(20 \times 16\right)$ women can complete the work in 1 day.
$\therefore$ 1 womans 1 days work =$ \dfrac{1}{320} $.
$\left(16 \times 15\right)$ men can complete the work in 1 day.
$\therefore$ 1 mans 1 days work =$ \dfrac{1}{240} $
So, required ratio =$ \dfrac{1}{240} $:$ \dfrac{1}{320} $
=$ \dfrac{1}{3} $:$ \dfrac{1}{4} $
= 4 : 3 [cross multiplied]
$\left(A + B + C\right)$s 1 days work =$ \left(\dfrac{1}{24} +\dfrac{1}{6} +\dfrac{1}{12} \right) $=$ \dfrac{7}{24} $.
So, all the three together will complete the job in$ \left(\dfrac{24}{7} \right) $ days=3$ \dfrac{3}{7} $days.
$\left(A + B\right)$s 1 days work =$ \left(\dfrac{1}{15} +\dfrac{1}{10} \right) $=$ \dfrac{1}{6} $.
Work done by A and B in 2 days =$ \left(\dfrac{1}{6} \times 2\right) $=$ \dfrac{1}{3} $.
Remaining work =$ \left(1 -\dfrac{1}{3} \right) $=$ \dfrac{2}{3} $.
Now,$ \dfrac{1}{15} $work is done by A in 1 day.
$ \dfrac{2}{3} $work will be done by a in 15 $\times \dfrac{2}{3} $ = 10 days.
Hence, the total time taken = $\left(10 + 2\right)$ = 12 days.
Ratio of rates of working of A and B = 2 : 1.
So, ratio of times taken = 1 : 2.
Bs 1 days work =$ \dfrac{1}{12} $.
As 1 days work =$ \dfrac{1}{6} $; [2 times of Bs work]
$\left(A + B\right)$s 1 days work =$ \left(\dfrac{1}{6} +\dfrac{1}{12} \right) $=$ \dfrac{3}{12} $=$ \dfrac{1}{4} $.
So, A and B together can finish the work in 4 days.
As 1 days work =$ \dfrac{1}{15} $;
Bs 1 days work =$ \dfrac{1}{20} $;
$\left(A + B\right)$s 1 days work =$ \left(\dfrac{1}{15} +\dfrac{1}{20} \right) $=$ \dfrac{7}{60} $.
$\left(A + B\right)$s 4 days work =$ \left(\dfrac{7}{60} \times 4\right) $=$ \dfrac{7}{15} $.
Therefore, Remaining work =$ \left(1 -\dfrac{7}{15} \right) $=$ \dfrac{8}{15} $.
$\left(B + C\right)$s 1 days work =$ \left(\dfrac{1}{9} +\dfrac{1}{12} \right) $=$ \dfrac{7}{36} $.
Work done by B and C in 3 days =$ \left(\dfrac{7}{36} \times 3\right) $=$ \dfrac{7}{12} $.
Remaining work =$ \left(1 -\dfrac{7}{12} \right) $=$ \dfrac{5}{12} $.
Now,$ \dfrac{1}{24} $work is done by A in 1 day.
So,$ \dfrac{5}{12} $work is done by A in 24 $\times \dfrac{5}{12} $= 10 days.
$\left(A + B + C\right)$s 1 days work =$ \dfrac{1}{6} $;
$\left(A + B\right)$s 1 days work =$ \dfrac{1}{8} $;
$\left(B + C\right)$s 1 days work =$ \dfrac{1}{12} $.
$\left(A + C\right)$s 1 days work =$ \left(2 \times \dfrac{1}{6} \right) $-$ \left(\dfrac{1}{8} +\dfrac{1}{12} \right) $
=$ \left(\dfrac{1}{3} -\dfrac{5}{24} \right) $
=$\dfrac{3}{24}$
=$\dfrac{1}{8}$.
So, A and C together will do the work in 8 days.
Work done by X in 8 days =$ \left(\dfrac{1}{40} \times 8\right) $=$ \dfrac{1}{5} $.
Remaining work =$ \left(1 -\dfrac{1}{5} \right) $=$ \dfrac{4}{5} $.
Now,$ \dfrac{4}{5} $work is done by Y in 16 days.
Whole work will be done by Y in$ \left(16 \times\dfrac{5}{4} \right) $= 20 days.
Xs 1 days work =$ \dfrac{1}{40} $, Ys 1 days work =$ \dfrac{1}{20} $.
$\left(X + Y\right)$s 1 days work =$ \left(\dfrac{1}{40} +\dfrac{1}{20} \right) $=$ \dfrac{3}{40} $.
Hence, X and Y will together complete the work in$ \left(\dfrac{40}{3} \right) $= 13$ \dfrac{1}{3} $days.
As 1 hours work =$ \dfrac{1}{4} $;
$\left(B + C\right)$s 1 hours work =$ \dfrac{1}{3} $;
$\left(A + C\right)$s 1 hours work =$ \dfrac{1}{2} $.
$\left(A + B + C\right)$s 1 hours work =$ \left(\dfrac{1}{4} +\dfrac{1}{3} \right) $=$ \dfrac{7}{12} $.
Bs 1 hours work =$ \left(\dfrac{7}{12} -\dfrac{1}{2} \right) $=$ \dfrac{1}{12} $.
B alone will take 12 hours to do the work.
Number of pages typed by Ravi in 1 hour =$ \dfrac{32}{6} $=$ \dfrac{16}{3} $.
Number of pages typed by Kumar in 1 hour =$ \dfrac{40}{5} $= 8.
Number of pages typed by both in 1 hour =$ \left(\dfrac{16}{3} + 8\right) $=$ \dfrac{40}{3} $.
Time taken by both to type 110 pages =$ \left(110 \times\dfrac{3}{40} \right) $hours
= 8$ \dfrac{1}{4} $hours [or] 8 hours 15 minutes.
Ratio of times taken by Sakshi and Tanya = 125 : 100 = 5 : 4.
Suppose Tanya takes $ x $ days to do the work.
5 : 4 :: 20 : $ x $ $\Rightarrow x $ =$ \left(\dfrac{4 \times 20}{5} \right) $
$\Rightarrow x $ = 16 days.
Hence, Tanya takes 16 days to complete the work.