Easy Tutorial
For Competitive Exams

X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?

13$ \dfrac{1}{3} $days
15 days
20 days
26 days
Explanation:

Work done by X in 8 days =$ \left(\dfrac{1}{40} \times 8\right) $=$ \dfrac{1}{5} $.

Remaining work =$ \left(1 -\dfrac{1}{5} \right) $=$ \dfrac{4}{5} $.

Now,$ \dfrac{4}{5} $work is done by Y in 16 days.

Whole work will be done by Y in$ \left(16 \times\dfrac{5}{4} \right) $= 20 days.

Xs 1 days work =$ \dfrac{1}{40} $, Ys 1 days work =$ \dfrac{1}{20} $.

$\left(X + Y\right)$s 1 days work =$ \left(\dfrac{1}{40} +\dfrac{1}{20} \right) $=$ \dfrac{3}{40} $.

Hence, X and Y will together complete the work in$ \left(\dfrac{40}{3} \right) $= 13$ \dfrac{1}{3} $days.

Additional Questions

A and B can together finish a work 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the work?

Answer

P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?

Answer

Twenty women can do a work in sixteen days. Sixteen men can complete the same work in fifteen days. What is the ratio between the capacity of a man and a woman?

Answer

A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in:

Answer

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :

Answer

A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in :

Answer

A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

Answer

A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

Answer

A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in :

Answer

X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?

Answer
Share with Friends
Privacy Copyright Contact Us