A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?

8 hours
10 hours
12 hours
24 hours
Explanation:

As 1 hours work =$ \dfrac{1}{4} $;

$\left(B + C\right)$s 1 hours work =$ \dfrac{1}{3} $;

$\left(A + C\right)$s 1 hours work =$ \dfrac{1}{2} $.

$\left(A + B + C\right)$s 1 hours work =$ \left(\dfrac{1}{4} +\dfrac{1}{3} \right) $=$ \dfrac{7}{12} $.

Bs 1 hours work =$ \left(\dfrac{7}{12} -\dfrac{1}{2} \right) $=$ \dfrac{1}{12} $.

B alone will take 12 hours to do the work.

Additional Questions

Ravi and Kumar are working on an assignment. Ravi takes 6 hours to type 32 pages on a computer, while Kumar takes 5 hours to type 40 pages. How much time will they take, working together on two different computers to type an assignment of 110 pages?

Answer

Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:

Answer

A can do piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it ?

Answer

A and B can together do a piece of work in 15 days. B alone can do it in 20 days. In how many days can A alone do it ?

Answer

8 children and 12 men complete a certain piece of work in 9 days. If each child takes twice the time taken by a man to finish the work, in how many days will 12 men finish the same work ?

Answer

12 men or 18 women can reap a field in 14 days. The number of days that 8 men and 16 women will take to reap it is

Answer

A can do a work in 14 days and working together A and B can do the same work in 10 days. In what time can B alone do the work?

Answer

Manu, Manju and Maya can do a work in 90, 30 and 45 days respectively. If they work together, in how many days will they complete work?

Answer

40 men can catch 200 sharks in 20 days working 6 hours a day. In how many days 25 men can catch 300 sharks working 4 hours a day?

Answer

Amit and Ananthu can do a work in 15 days and 25 days respectively. Amit started the work and left after 3 days. Ananthu took over and completed the work. In how many days was the total work completed?

Answer
Share with Friends
Privacy Copyright Contact Us