A can do a certain job in 12 days. B is 60% more efficient than A. How many days does B alone take to do the same job?

6 days
7 1/2days
8 days
8 1/2days
Additional Questions

If 5a=6; 6b = 7; 7c = 5, then find the value of abc.

Answer

The value of $\sqrt[x]{\sqrt[y]{\sqrt[z]{a}}}$ is

Answer

How much time will it take for an amount ₹2,000 to double at a simpleinterestrate

Answer

The length of a rectangle is increased by 60%. By what percent would the width have to be decreased so as to maintain the same area

Answer

A sum of Rs. 53 is divided among ABC in such a way that A gets Rs. 7 more than what B gets and B gets Rs. 8 more than what C gcts. Thc ratio of their share is

Answer

A cone, a hemisphcre and a cylinder stand an equal bases and have the same height. Find the ratio of their volunes

Answer

Select the pair, which are dimensionally alike among the following
I. Product of force and time
III. Product of momentum and time
III. Product of Ariel velocity and linear density
IV. Product of work and time

Answer

Arrange the following in the increasing order of their penetration powers
I. Alpha rays
II. Beta particles
III. Gamma rays

Answer

Match correctly the following Lists 1, 2 and 3 :

List 1List 2List 3
I. Ammonia(a) White solid(i) Rocket fuel
II.Basic reducing agent(b) Hydrazine(ii) Habers process
III.Explosive(c) Colourless volatile gas(iii) Hydrazoic acid
IV.Hydroxylamine(d) colouries volatile liquid(iv) Oxidising and reducing agent

Answer

Fructose-6-Phosphate is also known as

Answer
Share with Friends
Privacy Copyright Contact Us