16 men complete one-fourth of a piece of work in 12 days. What is the additional number of men required to complete the work in 12 more days ?
A takes thrice as long to do a piece of work, as B takes. A and B together can do a piece of work in 7.5 days. A alone can do in: |
Answer |
A cistern can be filled by two pipes A and B in 10 and 15 hours respectively and is then emptied by a tap in 8 hours. If all the taps are opened, the cistern will be fill in: |
Answer |
A locomotive engine, without any wagons |
Answer |
If 33 untrained labourers can do a work in 15 days of 12 hr. each, how many trained labourers can do 50% more work in 11 days of 9 hr each ? (It may be assumed that it takes 2 trained labourers to do the work of 5 untrained labourers) |
Answer |
Which of the following fractions is less than 7/8 and greater than 1/3 ? |
Answer |
892.7 - 573.07 - 95.007 = ? |
Answer |
Which is the closest approximation to the product 0.3333 x 0.25 x 0.499 x 0.125 x 24 ? |
Answer |
Find the value of X : |
Answer |
The least among the following is: |
Answer |
In the following expression, there are two missing digits: * and #. Find the value of *. |
Answer |