A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:

4 days
6 days
8 days
12 days
Explanation:

Suppose A, B and C take $ x $,$\dfrac{x}{2}$ and $\frac{x}{3}$ days respectively to finish the work.

Then,$ \left(\dfrac{1}{x} +\dfrac{2}{x} +\dfrac{3}{x} \right) $=$ \dfrac{1}{2} $

$\Rightarrow \dfrac{6}{x} $=$ \dfrac{1}{2} $

$\Rightarrow x $ = 12.

So, B takes $\left(12/2\right)$ = 6 days to finish the work.

Additional Questions

A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?

Answer

A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?

Answer

A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:

Answer

A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?

Answer

P,Q and R together earn Rs.1620 in 9 days. P and R can earn Rs.600 in 5 days. Q and R in 7 days can earn Rs.910. How much amount does R can earn per day?

Answer

A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:

Answer

A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work?

Answer

A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?

Answer

X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?

Answer

A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:

Answer
Share with Friends
Privacy Copyright Contact Us