A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?

Rs. 375
Rs. 400
Rs. 600
Rs. 800
Explanation:

Cs 1 days work =$ \dfrac{1}{3} $-$ \left(\dfrac{1}{6} +\dfrac{1}{8} \right) $=$ \dfrac{1}{3} $-$ \dfrac{7}{24} $=$ \dfrac{1}{24} $.

As wages : Bs wages : Cs wages =$ \dfrac{1}{6} $:$ \dfrac{1}{8} $:$ \dfrac{1}{24} $= 4 : 3 : 1.

$\therefore$Cs share [for 3 days] = Rs.$ \left(3 \times\dfrac{1}{24} \times 3200\right) $= Rs. 400.

Additional Questions

A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:

Answer

A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?

Answer

P,Q and R together earn Rs.1620 in 9 days. P and R can earn Rs.600 in 5 days. Q and R in 7 days can earn Rs.910. How much amount does R can earn per day?

Answer

A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:

Answer

A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work?

Answer

A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?

Answer

X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?

Answer

A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:

Answer

A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?

Answer

A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?

Answer