Easy Tutorial
For Competitive Exams

X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?

6 days
10 days
15 days
20 days
Explanation:

Work done by X in 4 days =$ \left(\dfrac{1}{20} \times 4\right) $=$ \dfrac{1}{5} $.

Remaining work =$ \left(1 -\dfrac{1}{5} \right) $=$ \dfrac{4}{5} $.

$\left(X + Y\right)$s 1 days work =$ \left(\dfrac{1}{20} +\dfrac{1}{12} \right) $=$ \dfrac{8}{60} $=$ \dfrac{2}{15} $.

Now,$ \dfrac{2}{15} $work is done by X and Y in 1 day.

So,$ \dfrac{4}{5} $work will be done by X and Y in $\left(\dfrac{15}{2}\times\dfrac{4}{5}\right) $= 6 days.

Hence, total time taken = $\left(6 + 4\right)$ days = 10 days.

Additional Questions

A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:

Answer

A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?

Answer

A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?

Answer

A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:

Answer

A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?

Answer

P,Q and R together earn Rs.1620 in 9 days. P and R can earn Rs.600 in 5 days. Q and R in 7 days can earn Rs.910. How much amount does R can earn per day?

Answer

A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:

Answer

A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work?

Answer

A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?

Answer

X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?

Answer
Share with Friends
Privacy Copyright Contact Us